Ward Eight By the Numbers

The following chart provides a break-down of development activity taking place in Ward Eight from 2001-2005. Data is provided for planned, proposed, under construction and completed projects.

Total Number of Projects 75
Total Project Cost $1,938,542,641
Total Square Feet 9,879,506
Status
# of Projects
Sq. Ft.
Est. Value
Completed 01
9
1,104,718
$305,651,861
Completed 02
15
1,934,000
$188,977,000
Completed 03
7
656,800
$76,675,000
Completed 04
7
438,100
$70,030,000
Under Construction
13
2,365,700
$328,380,580
Planned
17
2,256,188
$407,578,200
Proposed
7
1,125,000
$561,250,000
Type
# of Projects
Sq. Ft.
Est. Value
New Construction
42
5,311,710
$1,276,410,780
Renovation
31
4,567,796
$417,631,861
Infrastructure
2
n/a
$244,500,000
*totals by type may not sum to totals by status due to lack of information about planned and proposed projects.
Use
# of Projects
Sq. Ft.
Units
Infrastructure
2
n/a
Education
14
684,120
Hospitality
10
203,118
-Comunity
9
175,118
-Museum
1
28,000
Office
8
941,000
Residential
43
7,761,668
7,457
Retail
7
187,000

Posted Under: DC News